Resurfacing works to the Silverknowes-Blackhall path

Major resurfacing and drainage works are to take place on the cyclepath connecting Silverknowes and Blackhall.  The work will commence on 7th March and will last for approximately three weeks until 23rd March 2018.

The working hours will be between 0730hrs and 1730hrs Monday to Friday. There is no planned weekend working.

Potential path closures

Due to the nature of the works, officials have told us it will be necessary to  include footpath closures. Local diversions around work activities (may require dismounting and walking on verges)

  1. Path closures – with diversion routes taken between accessible ramp accesses.  Please see this diversion map 
  2. Information boards will be displayed at closure points with maps of the diversion routes for onward journeys.  Please note that some diversion routes may require cycling on trafficked roads and dismounting for crossings.