Burnshot bridge update – October

We have received the following update from officials on the Burnshot Bridge.

Progress Update No 5
4 October 2017

Introduction
This note provides an update to Progress Update No 4 (attached for ease of reference).

Monthly Inspections
These inspections are ongoing to closely monitor the condition of the bridge soffit. Inspections will continue until the bridge is demolished.

Traffic Diversion
Installation of the new semi-permanent signage is currently taking place on site and this will continue over the coming weeks.

Demolition Works
Plans for the demolition are now well underway. Following market testing to ensure value for money for the Council, the Contractor has now made preliminary arrangements with Subcontractors for traffic management, site clearance, temporary service bridge installation, and the actual demolition Works. Whilst still subject to contract, preliminary work is expected to commence in late-October, with the demolition of the bridge in November.
Public Utilities (PUs)

The Council and the Contractor have now met with all utilities companies on site and agreed the methodology for suspension or diversion of the affected services; these include Virgin Media and Vodafone ducts, and a Scottish Power cable. These Works have all been planned so that there should be no disruption to customers’ services.
Vegetation Clearance

As reported in the interim update via email on 30th August, in preparation for the demolition works, it will be necessary to complete some vegetation clearance either side of the bridge to facilitate:
a) Installation of the service bridge, and
b) Access for demolition equipment

No disruption to residents or road users is anticipated.

Community Liaison
Plans have been made to hold an open event for residents in close vicinity of the bridge who may wish to find out more about the demolition. The date for this is to be confirmed; affected residents will be notified by a letter drop in the coming weeks.